MORAGA, Calif. – Following an intense four months of construction over the summer, the initial phase of the Student Athlete Performance Complex was completed right on schedule and ready for the fall athletic season to begin.
The work involved in Phase One primarily focused on McKeon Pavilion, which received major upgrades to the 40-year old structure.
Gael supporters now entering McKeon Pavilion will notice dramatic differences, including the installation of a new state-of-the-art Daktronics video board, spanning 48-feet wide on the east side of the building.
A new Daktronics sound-system was installed to help enhance the sound quality inside the pavilion, including the lobby and restrooms.