$3 billion Salt Lake airport rebuild hits midway mark and future begins to take shape

Related Topics: program director

“It’s getting exciting now,” said Mike Williams, airport redevelopment program director, as he looked over vast fields of new foundations, support columns, a small army of 600 workers, 19 cranes lifting steel and supplies, and several buildings rising from the ground.

(Francisco Kjolseth | The Salt Lake Tribune) The Salt Lake City Department of Airports gives a tour of the progress being made to replace the three aging terminals with a single central terminal building. Over time, the existing terminal, parking garage and concourses will be completely demolished and replaced with an estimated completion date of 2023/24.