With the weather turning — at last — to spring, we thought it would be a good time to check in on the recent progress on Allianz Field. On April 19 last week, we passed the halfway point in the construction timeline and the physical construction is on pace to pass the halfway point in the next few weeks.
Those who pass by the site regularly will notice that the large yellow crane that was a major part of installing the structural precast has come down with the completion of that work. The steel structure has been installed and detail work has begun, with the only remaining steel work being the canopy that goes over the top, which is about 75% complete.