Aw, nuts.
The LA Times is reporting that Stan Kroenke’s 2.6 billion dollar Inglewood NFL palace has been delayed a year due to record rainfall, which temporarily halted the project at the worst possible time.
The weather brought work on the project to a standstill for two months earlier this year. The rain fell at a crucial stage of construction when work centered on digging the enormous hole — 5 million cubic yards of dirt were excavated — in which the stadium will sit. At times, the site looked like a lake, with water standing 12 to 15 feet deep.