Clemson Athletics is in the process of ongoing capital projects totaling $106 million, with several facilities on schedule for completion in the coming weeks. Below is a status update on each of the projects. Up-to-date pictures and renderings of each of Clemson’s athletics facilities upgrades can be found at the “Expand and Enhance” page on ClemsonTigers.com.
DOUG KINGSMORE STADIUM
Players are scheduled to move into the new facility as school starts on Aug. 19. Located down the first base line, the 20,000 square-foot complex includes locker rooms, team areas, training room, a dining area, meeting space, a catering kitchen, laundry, coaches offices, and a player’s lounge.