BCB’s Sara Sanchez visited Wrigley Field earlier Thursday, took the photos above, and filed this report:
It’s been pretty gray and dreary around the ballpark for most of the week, but that hasn’t put a damper on the work the crews are doing in the off-season. There are three main areas of activity as of the first week in December.
The busiest corner of the ballpark is still the right field corner near Sheffield and Addison. There are a lot of crews and truck activity in this area. The scaffolding continues to move down the side of the park.